Finished block retaining wall along the fence line with the side yard regraded
2024

Bellevue Block Wall

A new reinforced CMU (cinder block) wall along a hillside side-yard in Bellevue, Washington — roughly 200 linear feet of footing excavation, formed and rebar-tied footings, grouted block, and slope stabilization to hold back the grade and square up a tight side yard. Built in 8 working days.

Wall length
200 ft
Build time
8 days
Completed
2024
Jurisdiction
City of Bellevue / King County
Photos
5 photos
The project story

Masonry / Block Wall in Bellevue, WA

How the job started, what our in-house crew built, and how it turned out.

01Site & challenge

A hillside side yard in Bellevue had become an unusable strip of mud: the cut slope above it was raw, the grade sloped toward the house, and there was nowhere for water to go. The owners needed roughly 200 linear feet of retaining wall along the fence line to hold the bank, square up the yard, and drain properly — and they wanted it done fast, before the wet season turned the slope into a bigger problem.

02What we built

We protected the cut slope with membrane and erosion control first, then trenched to bearing along the full 200 feet and set long, straight wooden forms with continuous rebar for a concrete footing. Once the footing cured, our crew laid reinforced CMU block course by course, keeping steel continuous through the cells and grouting the wall solid to code, with a mini excavator handling block and backfill in the tight corridor. Drainage rock and pipe went in behind the wall before we regraded the side yard to a finished grade that sheds water away from the foundation. The wall was engineered and permitted through our in-house engineering and permitting team and built under our concrete and masonry service.

03Outcome

Eight working days from the first trench to final grade, the once-muddy side yard is a flat, dry, usable strip held by a reinforced block wall permitted through the City of Bellevue and King County. Wet, sloped Bellevue lots put real pressure on a side-yard wall; this one is built to hold.

Photo gallery

5 photos from the job

Bellevue Block Wall 3d flythrough video still — Masonry / Block Wall in Bellevue, WA3D flythrough
Crew member beside the long footing form in a Bellevue side yard, with the cut slope covered in white membrane
1 / 5

Crew member beside the long footing form in a Bellevue side yard, with the cut slope covered in white membrane

Planning something similar?

Get a planning-level range for a masonry / block wall like this one — free, about 90 seconds, adjusted for your ZIP.

Price a project like this Open in 3D Design Studio
Scope by trade
Excavation & footing
Trenched and formed a continuous, rebar-tied concrete footing along the ~200-ft wall line
CMU block & grout
Laid and steel-reinforced cinder-block courses, grouted solid to code
Slope stabilization
Shored and protected the cut slope with membrane and erosion control while the wall went up
Site & drainage
Graded the side yard, set drainage behind the wall, and cleaned up to a finished grade

The challenge

Bellevue's wet, sloped lots put real pressure on a side-yard wall. We trenched to bearing along roughly 200 feet, tied continuous steel, and grouted the block solid — stabilizing the cut slope with membrane and drainage so the finished wall holds the grade and squares up a once-muddy side yard, start to finish in just 8 days.